We hold weekly neighbourhood meetings with floor / department representatives to give you the most up to date information and to present a forum for you to give us feedback. Invitations to this meeting are sent via email. To be added to the invite list please email your request to the project manager, Emeka Okorocha, at e.okorocha@ucl.ac.uk.
| ID |
Task Name |
March 2013 |
Week 26 |
|
| |
|
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
01 |
| 1 |
Breaking out Floor in Riser A & B All Floors 7-10pm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Breaking out Floor in Riser A & B 10th Floor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
Chasing 1st Floor Corridor at Staircase Ends |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 4 |
Install SWA Cabling Basement to Roof in Plant Room Riser C |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 5 |
Riser B Shutdown 6th Floor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 6 |
Install HL Containment within Ceiling Void 1st Floor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 7 |
Working within agreed Rooms 1st Floor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 8 |
Containment & Wiring in Roof Plant Room |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 9 |
Install HL Electrical containment & Cabling Basement Ceiling Void |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
WP Installation works within Lateral Risers A,B & C. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 11 |
Riser A Shutdown 6th Floor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 12 |
Install SWA's in 1st Floor Ceiling Void |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 13 |
Remove 9th floor Ceiling & install Temporary Lighting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 14 |
ITC Decorating to the 4th, 5th, 7th & 8th Floors |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 15 |
ITC Works to Doors & Frames 6th Floors |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 16 |
Firestopping 6th & Basement Floors |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 17 |
ITC Works to Doors & Frames 1st Floor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 18 |
Arco Commence Asbestos Removal floors 3,4,5,6,&7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|