Queen Square House Infrastructure Projects Notice Board

Welcome to the project information page for the emergency systems upgrade for Queen Square House. This page will be updated regularly to keep you up to date with the progress of the work and give you a 2 week look ahead into what is coming up.

We hold weekly neighbourhood meetings with floor / department representatives to give you the most up to date information and to present a forum for you to give us feedback. Invitations to this meeting are sent via email. To be added to the invite list please email your request to the project manager, Emeka Okorocha, at e.okorocha@ucl.ac.uk.

For more detailed info about the project please download the Neighbourhood Meeting Presentation (PDF).

What is coming up in the next two weeks?

ID

Task Name

March 2013
Week 26

Week 27

   
18
19
20
21 22 23 24
25
26
27
28
29
30
31 01
1 Breaking out Floor in Riser A & B All Floors 7-10pm                              
2 Breaking out Floor in Riser A & B 10th Floor                              
3 Chasing 1st Floor Corridor at Staircase Ends                              
4 Install SWA Cabling Basement to Roof in Plant Room Riser C                              
5 Riser B Shutdown 6th Floor                              
6 Install HL Containment within Ceiling Void 1st Floor                              
7 Working within agreed Rooms 1st Floor                              
8 Containment & Wiring in Roof Plant Room                              
9 Install HL Electrical containment & Cabling Basement Ceiling Void                              
10 WP Installation works within Lateral Risers A,B & C.                              
11 Riser A Shutdown 6th Floor                              
12 Install SWA's in 1st Floor Ceiling Void                              
13 Remove 9th floor Ceiling & install Temporary Lighting                              
14 ITC Decorating to the 4th, 5th, 7th & 8th Floors                              
15 ITC Works to Doors & Frames 6th Floors                              
16 Firestopping 6th & Basement Floors                              
17 ITC Works to Doors & Frames 1st Floor                              
18 Arco Commence Asbestos Removal floors 3,4,5,6,&7                              
WP Task
 
ITC
 
Arco
 
Shut Down
 

UCL Project Team Contact Details

Darren Walker UCL Estates darren@dewalkerassociates.co.uk Clerk of Works
Martin Jerred UCL Estates m.jerred@ucl.ac.uk Facilities Manager
Colin Boekbinder UCL Estates c.boekbinder@ucl.ac.uk Group Manager Satellite Estates
Emeka Okorocha UCL Estates e.okorocha@ucl.ac.uk  Project Manager
Connor Wilson UCL Estates connor.wilson@ucl.ac.uk Capital Projects Team Leader

Stop Work Procedure

For any works that are outside the agreed noise limits and times please see the Stop Work Procedure (PDF) to voice your concerns and have works investigated.

Project Progress Photos