Welcome to the project information page for the emergency systems upgrade for Queen Square House. This page will be updated regularly to keep you up to date with the progress of the work and give you a 2 week look ahead into what is coming up.
We hold weekly neighbourhood meetings with floor / department representatives to give you the most up to date information and to present a forum for you to give us feedback. Invitations to this meeting are sent via email. To be added to the invite list please email your request to the project manager, Emeka Okorocha, at e.okorocha@ucl.ac.uk.
For more detailed info about the project please download the Neighbourhood Meeting Presentation (PDF).
What is coming up in the next two weeks?
ID |
Task Name |
Dec 13 |
Week 55 |
Week 56 |
|
|
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
01 |
02 |
03 |
1 |
Shutdown to Riser 'A' Ess & NonEss Basement to 4th Floors |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 |
Strip out old Fire Alarm Ground andbasement
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
Containment & Wiring in Roof PlantRoom
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
WP Installation works within LateralRisers A,B & C.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
Install HL Electrical Cabling withinBasement Main Switch Room
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6 |
Commissioning Mains MeteringSystem
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 |
W.Portsmouth X-Mas Break |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Install Lighting in Riser C
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9 |
TC General Snagging |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
Fitting Missing Ironmongery
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11 |
Dusty Works- Outside ElectricalRisers A,B & C all Floors, BasementCorridors,Plant Rooms 11th Floor,5th Floor corridors outside rooms527,8,9 & 510,11,12,13 & 14
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WP Task |
|
ITC |
|
Arco |
|
Shut Down |
|
Dusty Works |
|
UCL Project Team Contact Details
Stop Work Procedure
For any works that are outside the agreed noise limits and times please see the Stop Work Procedure (PDF) to voice your concerns and have works investigated.
Project Progress Photos
|
|