Significant building and refurbishment works are taking place across campus over the summer following the end of this academic year.

Quad Birds eye

Here is a summary of the works that are beginning over the summer:

Wilkins Octagon and Oculus

  • Opening up the Oculus and creating exhibition space at the heart of the Wilkins building.

Darwin

  • 6th floor Computational Biology suite
  • 4th floor laboratory for biology and basement peptide synthesis facility

50/51 Gordon Square

  • Refurbishment for the Institute of Americas

1-4 Malet Place

  • Data laboratory facility for the Jill Dando Institute

Medical Sciences & Anatomy

  • 4th floor and basement laboratories for Biosciences

Chadwick Building

  • Works to create a basement Geotechnics laboratory

Former Royal Ear Hospital

  • Work for Bartlett to create warehouse type fit out on ground, second and third floors

The Podium, Eversholt Street

  • 1st floor fitting out

External redecoration and repair contract - Bloomsbury Campus

  • Scaffolding will be erected on the North and South elevations of the Medical Sciences Building and the Malet Place elevations of Egyptology for a programme of external redecoration and repairs

1-19 Torrington Place

  • Concrete repair and external redecoration - scaffolding will be erected on the 11 storey elevations of the building for repairs to the concrete columns and panels and redecoration of windows etc.
  • Replacement of heating boilers and clorifiers in basement plant room.
  • Replacement of life expired versatemp units.
  • Upgrade to lighting controls.

Christopher Ingold Building

  • Renewal of roof coverings
  • Replacement of chiller unit on roof.
  • Replacement of air handling units to main lecture theatres

Bentham House

  • Installation of pipe work and radiators for new heating system

Replacement of passenger lifts

  • Chadwick Building
  • Darwin Building
  • 25 Gordon Street
  • Central Collegiate Building
  • MRC Building

3-4 Taviton Street

  • Installation of new fire alarm system and emergency lighting

Gordon House

  • Renewal of boilers in basement plant room and water hygiene works

Roberts Building

  • Phase 3 of renewal of heating system

ACBE Building

  • Renewal of steam and condense infrastructure.
  • Replacement of fan coil units.

Medical Sciences

  • Electrical switchgear and distribution replacement

Malet Place Engineering

  • Modifications to existing heating mains

Malet Place/Anatomy yard

  • Replacement of combined heat and power transformers, and relocation of units to external compound opposite boiler house

Rockefeller Building

  • Repair of main roof covering

Greg Beach, Director of Capital Projects and Ana De'Ath, Engineering & Maintenance Team Leader, UCL Estates